Application of funds

INFORMATION on the work carried out under the Resolution of the President of the Republic of Uzbekistan dated September 18, 2021 No. RP-5246 “On measures to implement “Sustainable Rural Development” Project with the participation of the Islamic Development Bank and OPEC International Development Fund”

01/04/2025

thousand USD

# Project Components The total cost of the project Disbursed funds as of January 1, 2025 Disbursement of funds for 2025
Plan Fact
SUMMARY: 275,000 34,023 135,000 9,879
1-komponent: Access to Basic Infrastructure and Services
1 A1-component: Block Investment for Rural Infrastructure Development 204,250 15,965.0 118,669.0 5,806.0
2 A2-component: Market Infrastructure Development 40,000 8,641.0 6,622.0 2,839.0
2-komponent: Engineering Services and Strengthening Capacity in Infrastructure Management
3 B1-component: Engineering Services (Planning, Design & Supervision) 11,050 3,066.0 9,017.0 1,106.0
4 B2-component: Strengthening Capacity in Sustainable Management of Infrastructure, M&E 7,300 5,000.0
5 "3-5 components: Project Management Support, Contingency Emergency Response and Financial Audit Service" 12,400 1,351.0 692.0 128.0

Project implementation period: 2021–2025.